Phase 2 (new!)
Test No. Starting Date / Time Status Real-time Plots Videos Note
Local UTC
1 2009/1/17 10:00 am 2009/1/17 2:00 am Finished Open...    
2 2009/3/28 9:00 am 2009/3/28 1:00 am Finished Open...    
3 2009/5/16 9:00 am 2009/5/16 1:00 am Finished Open...    
4 2010/6/1 10:30 am 2010/5/25 2:00 am Finished Open...   50-gal LA03 hybrid simulation implemented by OpenSees and OpenFresco
5 2010/6/02 4:00 pm 2010/06/02 8:00 am Finished Open...   50-gal LA03 hybrid simulation implemented by ISEE(PNSE)
6 2010/6/12 9:30 am 2010/06/03 1:30 am Finished Open...   530-gal LA03 hybrid simulation implemented by ISEE(PNSE)
7 2010/8/23 10:00 am 2010/8/23 2:00 am Finished Open...   50-gal LA03 hybrid simulation implemented by ISEE(PNSE) for the repaired specimen
8 2010/8/29 10:00 am 2010/8/29 2:00 am Finished Open...   530-gal LA03 hybrid simulation implemented by ISEE(PNSE) for the repaired specimen
9 2010/8/29 1:00 pm 2010/8/29 5:00 am Finished Open...   Cyclic Test
10 2010/10/8 9:00 am 2010/10/7 1:00 am Preparing Open...   5mm Free vibration test
11 2010/10/8 13:30 am 2010/10/7 5:30 am Preparing Open...   50-gal LA03 hybrid simulation
12 2009/10/16 9:00 am 2010/10/16 1:00 am Preparing Open... Live #1
Live #2
597-gal LA03 hybrid simulation
13 2010/10/16 14:00 am 2010/10/16 6:00 am Preparing Open...   Cyclic Test


Phase 1...
Test No. Starting Date / Time Status Real-time Plots Videos
Local UTC
1 2007/12/12 10:00 am 2007/12/12 2:00 am Finished Open...  
2 2007/12/18 9:30 am 2007/12/18 1:30 am Finished Open...  
3 2008/4/10 9:00 am 2008/4/10 1:00 am Finished Open...  
4 2008/11/22 8:30 am 2008/11/22 0:30 am Finished Open...  
 